Sapphire inspection references: keep the agreed document edition with the requirement
Identify the governing reference
When a sapphire substrate drawing invokes an external inspection reference or a customer procedure, identify the exact document and edition that govern the order. Avoid an abbreviated note that different teams could interpret differently. Ask the supplier to review the referenced scope before quotation and record any exception instead of assuming that an unspecified company practice will match it.
Connect the reference to a feature
State which surface, region or characteristic the reference applies to. Keep dimensional requirements, visual observations and material documentation distinguishable. If the project uses more than one inspection reference, show how each is assigned. A reference list alone does not explain which rule a receiving inspector should apply to a particular observation.
Control changes in interpretation
If an edition or internal procedure changes during the order, identify which deliveries are affected and obtain the relevant approval. Preserve the reference used for the original quotation. Do not apply a later inspection interpretation to already supplied material without reviewing the contractual requirement and the scope of the proposed change with the responsible parties.
Prepare a receiving reference card
A receiving reference card can name the part revision, applicable inspection document and edition, inspected face or region, required report and responsible reviewer. Keep it with the released drawing. When a question arises, send the specific clause or procedure reference with the observation so the supplier can answer the same question that the buyer is evaluating.